MARITIME RESCUE VESSEL INSPECTIONS AND ACCEPTANCE

Koko: px
Aloita esitys sivulta:

Download "MARITIME RESCUE VESSEL INSPECTIONS AND ACCEPTANCE"

Transkriptio

1 SPECIFICATION Lasse Kämäräinen MARITIME RESCUE VESSEL INSPECTIONS AND ACCEPTANCE - inspections during building - acceptance inspections and tests - delivery documentation - vessel acceptance procedure - user training SUOMEN MERIPELASTUSSEURA RY FINLANDS SJÖRÄDDNINGSSÄLLSKAP RF THE FINNISH LIFEBOAT INSTITUTION 1 / 21 Kalliolinnantie 4, FIN Helsinki, Finland smps.toimisto@meripelastus.fi Bank account details: Nordea Sampo The Central Organisation for Voluntary Maritime Rescue Associations Founded in 1897 Business ID The Finnish Lifeboat Institution

2 CONTENTS 1. GENERAL INFORMATION Inspection and testing arrangements INSPECTIONS AND TESTS DURING BUILDING The supplier's own inspections during building The buyer's inspections during building Inspections, testing and measuring during building Hull welding seam quality inspections (vessels with metal or polyethylene hulls) Hull laminate testing (vessel with reinforced plastic hull) Hull inspection Welding seam x-rays (vessel with a metal hull) Painting work monitoring and paint coat measuring (vessel with a metal hull) Laminate thickness inspection (vessel with reinforced plastic hull) Leak tightness tests Early inspector visits SMPS hull inspection Earthing measurements Insulation resistance measurements INSPECTIONS AND TESTS TO BE PERFORMED AT THE TIME OF ACCEPTANCE OF THE VESSEL The supplier's own technical inspections, functional tests, measurements and tests before acceptance Functional tests of installed equipment Inventory and inspection of the boat's equipment and equipment mounting functionality tests The buyer's technical acceptance inspections Tests and measurements to be taken at the time of acceptance of the vessel Docking tests Drop test Weighing Leak tightness tests Stability tests Corrosion protection measurements (vessel with a metal hull) Battery load testing Bilge pump and bilge water level sensor function tests Sea trials Main engine performance tests Main engine installation inspection and functional analysis The buyer's sea trial Inspections The SMPS basic inspection Inspection by the Finnish Transport Safety Agency Trafi Trial period DELIVERY DOCUMENTATION Delivery documentation list Electronic delivery documentation format / 21

3 4.3 Inspection of delivery documentation Changes made after the delivery documentation has been handed over ACCEPTANCE OF THE VESSEL USER TRAINING Training contents Training dates Training resources Training location Training costs ATTACHMENTS 1. The timing of measurement and inspection activities in relation to the building work schedule (example) 2. Sea trial schedule/report 3. Guide of content tables and folder structure for the delivery documents 4. User training programme (example) 3 / 21

4 1. GENERAL INFORMATION 1.1 Inspection and testing arrangements The inspections and testing of the Finnish Lifeboat Institution's new vessels during building and acceptance and any related procedures will be carried out according to the instructions given in this specification, unless otherwise agreed in the procurement contract or its attachments. This specification also includes information on the delivery documents and user training. The applicable parts will also be, to the necessary extent, applied to work done while overhauling or updating the buyer's vessels. During the work process, changes to these procedures can only be made with the buyer's written confirmation. The schedule attached to this document offers an example on how the inspections and acceptance-related activities can be timed in relation to the work schedule (attachment 1). The supplier is responsible for making arrangements, performing, providing the equipment and covering the costs of any testing and inspections unless, in the procurement contract or its attachments or this specification, the buyer is specifically stated to be responsible for performing of paying for the tests. If, in the technical specification or other contract documents (or other instructions regarding the building process), the vessel is defined as needing to be inspected by an inspection body, the supplier is responsible for the practical arrangements, scheduling and other arrangements unless otherwise agreed in the procurement contract, or with the buyer during the project. Selection of the inspection body, inspection commissioning and the inspection costs are the buyer's responsibility unless otherwise agreed in the procurement contract documents. If the tests or inspections performed by the buyer or an inspection body selected by the buyer, or inspections performed by inspectors, need to be repeated or agreed inspection times cancelled due to the supplier's actions, the supplier is responsible for the resulting costs. 2. INSPECTIONS AND TESTS DURING BUILDING During the building process, as the work progresses through the different phases, inspections will be performed by both the supplier and the buyer. At the minimum, the inspections carried out by the buyer or an inspection body selected by the buyer must be presented in the work phase schedule. Potential changes and more specific information on the timing of the buyer's inspections must be agreed on at least 14 days beforehand with the buyer's representative. 2.1 The supplier's own inspections during building The supplier must inspect all of their own work and installations during the entire building process. Special attention must be paid to installations that will be concealed and the main work phases are also to be inspected by the buyer (see section 2.2). 4 / 21

5 The supplier must document all of their own inspections (by writing reports). The inspection documents should also contain photographs, especially of the concealed installations. The supplier's inspection reports will be presented to the buyer when the technical acceptance inspections begin. 2.2 The buyer's inspections during building The buyer inspects all of the main work phases during the building of the vessel: hull inspection once the hull is completed, including the inspections of the welding seams and drainage holes (in small boats and RIB boats this must be done before the deck structure is attached to the rest of the boat if it will no longer be possible to perform all the inspections under the deck once the deck is attached) main engine, power transmission and propulsion installations joining the wheelhouse to the deck all welding seams, joints and installations that will be concealed and cannot reasonably be accessed at a later stage hull inspection according to the SMPS guidelines once the painting of the vessel s bottom has been completed Depending on the available resources, the buyer will carry out additional inspection and monitoring activities during building so that any discovered issues can be addressed together with the supplier as soon as possible. 2.3 Inspections, testing and measuring during building The following tests and inspections are to be carried out during building. They must be in compliance with the Commercial Craft Rules and the provisions below. The tests and measurements must be recorded in writing. The measurement reports must also include the measuring results (not just accepted/failed). The measurements must be performed using calibrated equipment. The supplier will present the buyer with calibration certificates. If the supplier has the capacity to perform adequate calibrations themselves, this can be done. If not, certified calibration providers must be used Hull welding seam quality inspections (vessels with metal or polyethylene hulls) Before the building of a metal hull and welding work can commence, the materials and methods intended to be used must undergo procedure qualification (WPS) according to the Commercial Craft Rules' specifications. The requirement applies to vessels that are subject to it according to the Commercial Craft Rules. The procedure qualification tests for critical hull parts and work phases must be performed to a satisfactory extent as determined by the buyer. The test pieces are to be sent to an inspection body selected by the buyer for inspection and testing. The costs charged by the inspection body are the buyer's responsibility. 5 / 21

6 If a series of vessels is being manufactured, the procedure qualification tests are only performed during the building of the first vessel, assuming that the structures and work methods remain the same. If the buyer and the supplier agree to make changes that affect the reliability of the previously performed tests, the tests must be repeated where necessary. If the supplier can provide acceptable documentation to prove that they have had applicable procedure qualification tests performed earlier for similar structures and methods and by an acceptable inspection body, these will be recognized. The aforementioned procedure will also be applied to polyethylene-hulled vessels as a modified version Hull laminate testing (vessel with reinforced plastic hull) Before manufacturing the hull, test pieces from at least three places chosen by the buyer must be manufactured according to the lamination plan. The test pieces are to be sent to an inspection body selected by the buyer for inspection and testing. The strength properties of the test pieces will be tested based on the structure's design calculations. The costs charged by the inspection body are the buyer's responsibility. If a series of boats is being manufactured, the tests are only performed on the first boat assuming that the structures, materials and work methods used remain the same. If the buyer and the supplier agree to make changes that affect the reliability of the previously performed tests, the tests must be repeated where necessary. If the supplier can provide acceptable documentation to prove that they have had applicable procedure qualification tests performed earlier for similar structures, materials and methods and by an acceptable inspection body, these will be recognized Hull inspection Once the hull is fully completed below the deck and up to the deck level, the hull will undergo visual inspection of the structures and laminating or welding work. If the vessel is a small boat or a RIB boat, the inspection shall be performed before the deck is attached in case it will no longer be possible to access the space below the deck for inspections after the deck is attached. The inspection is to be performed before any equipment installations or outfitting work are performed on the empty hull. However, any equipment that will be welded to the hull, e.g. propulsion, must be installed so that the welding work can also be inspected. The inspection will be performed by the buyer's representative and a representative of the inspection body selected by the buyer. The costs charged by the inspection body are the buyer's responsibility. After the inspection, while the buyer is present, the drainage holes will be inspected. The inspection will be performed by spraying water (not seawater) with a hose into all compartments and then checking that no water remains on any longitudinal or transverse stringers. All water must flow to the lowest point in the bilge. In order to check the drainage holes, the hull must be positioned horizontally in the transverse direction and in the intended floating position in the longitudinal direction. 6 / 21

7 2.3.4 Welding seam x-rays (vessel with a metal hull) After the hull inspection, the hull's welding seams will be inspecting by taking x-rays according to the Commercial Craft Rules' specifications. This requirement applies to vessels that are subject to it according to the Commercial Craft Rules. The x-rays must be taken by a qualified and approved inspection body or other similar actor. X-rays shall be taken at several points, with the points to be x-rayed decided by the buyer or the inspection body selected by the buyer. The Commercial Craft Rules' specifications are to be followed when assessing welding seam quality and quality class. The assessment is to be performed by the inspection body selected by the buyer, based on both the x-rays and the written report by the inspector who took the x-rays. If poor quality areas can be identified based on the x-rays, two more x-rays can be taken of the area in question at the buyer's request. The general principle in these cases is that the faulty structure should be removed and replaced. If the buyer explicitly accepts it, the welding seam can be locally repaired. When repairing a faulty welding seam, it must be opened and re-welded so that no harmful tension is created in the metal structures. Repaired seams must be x-rayed again. The areas to be inspected are to be documented by the supplier in the vessel's hull plans and the x-rays must be handed over to the buyer Painting work monitoring and paint coat measuring (vessel with a metal hull) The supplier or painting contractor must keep a painting journal. The painting journal should include, at a minimum: reporting the conditions the painting work was performed under (temperature, humidity, dew point and wind), checking the paints and shades used (vs. the buyer's painting specification and the agreed paints) and inspecting the cleanliness and priming of the surface to be painted. Paint coat thickness measurements will be performed by the supplier or the painting contractor after both the primer and the top coat (wet and dry film thickness). The purpose of the measurements is to ensure that the paint coats are at least as thick as required by the buyer's painting specification and the manufacturer's instructions, yet not overly thick. The sufficient number and locations of the points to be measured are indicated and approved by the buyer beforehand using e.g. the painting schematics. The supplier or painting contractor must provide paint coat measurement records where the values are marked on the vessel's painting scheme or general arrangement drawings (GA). The measurement records are to be attached to the painting report that is delivered to the buyer. 7 / 21

8 The buyer will perform spot-check measurements using their own equipment during the acceptance inspection Laminate thickness inspection (vessel with reinforced plastic hull) Once the hull is completed, the laminate thickness will be measured at a sufficient number of different points according to the Commercial Craft Rules' instructions. The measurements shall be taken by a representative of the inspection body the buyer has selected. The costs charged by the inspection body are the buyer's responsibility Leak tightness tests The supplier is expected to perform the following leak tightness tests themselves: The leak tightness tests of the hull and any potential air pontoons, waterproof compartment bulkheads and other waterproof structures is to be performed using pressure tests (pontoon boats) or oil chalk testing if the tested areas cannot be pressurized (e.g. covered or partially covered boats). The fuel tank leak tightness test must be performed according to the Commercial Craft Rules' requirements. The fuel system leak tightness test must be performed according to the Commercial Craft Rules' requirements. The septic tank's leak tightness test must be carried out according to the Commercial Craft Rules' requirements, similarly to the fuel tank. The fresh water tank's leak tightness test must be carried out according to the Commercial Craft Rules' requirements, similarly to the fuel tank Early inspector visits For the first vessel in a series, an SMPS vessel inspector or inspector will visit the vessel during construction at a time explicitly decided by the buyer when installations that will later be concealed are still visible on the vessel. If, according to the technical specification, the vessel is to be inspected by the Finnish Transport Safety Agency Trafi, Trafi's inspector may visit the vessel during construction at a time explicitly agreed with the buyer. At the chosen time, the installations that will later be concealed should still be visible. The costs of these inspections are the buyer's responsibility SMPS hull inspection After propulsion is installed and the hull bottom painted (all work below the gunwale or pontoon is completed) and before the vessel is launched, the buyer will organize a 8 / 21

9 hull inspection according to the SMPS (Finnish Lifeboat Institution) inspection system. The inspection will be performed by an SMPS vessel inspector or SMPS's own inspector. The costs charged by the inspector are the buyer's responsibility Earthing measurements The supplier or the electrical contractor must perform earth resistance measurements according to the Commercial Craft Rules' requirements. The measurements need to be sufficiently extensive and performed by measuring the resistance between the earthed current-using equipment and the earthing electrode. The earthing resistance may not exceed 0.05 ohm Insulation resistance measurements The supplier or the electrical contractor must perform insulation resistance measurements to all groups going out from the central electric unit, according to the Commercial Craft Rules. The insulation resistance must be at least 1 kω/ V. With regard to the electronics installed into the vessel, special care must be taken to not harm them while performing the measurements. If the vessel's electrical systems have been installed so that they employ bus technology controls and/or outputs using semiconductor technology, the way the insulation resistance measurements shall be carried out (or not performed at all) must be discussed with the buyer. 3. INSPECTIONS AND TESTS TO BE PERFORMED AT THE TIME OF ACCEPTANCE OF THE VESSEL Before acceptance inspections and tests can be performed, the vessel must be fully completed and equipped according to the technical specifications. The buyer will not start performing inspections on a vessel that is not completed or fully equipped. At least three (3) weeks need to be reserved for the buyer's tests and inspections at the end of the project, so that the supplier has time to correct any flaws or deficiencies discovered during the inspections and testing before the vessel is accepted according to the procurement contract. If the procurement contract includes a testing period for the first vessel in a series (see section 3.5), this must be taken into account between the buyer's tests and inspections and the acceptance inspection. The timing for the acceptance inspections must be presented in the work phase schedule (or a separate acceptance procedure schedule). Acceptance-related inspections are to be scheduled so that they are performed in stages and in the order described in this document, within the allowed timeframe and without overlapping inspections. If the agreed inspection dates need to be changed by the supplier during the project, this must be agreed on at least 14 days beforehand with the buyer and the inspectors and the schedule must be updated. 9 / 21

10 3.1 The supplier's own technical inspections, functional tests, measurements and tests before acceptance Before the buyer's acceptance inspections the supplier must, well in advance, check all of the vessel's installations, equipment, systems and outfitting. The inspections should be carried out according to the buyer's inspection and test guidelines and the structures, systems and equipment should be checked in the order they are presented in the specifications so that everything gets checked. The inspections and functional tests must be recorded in reports that will then be provided to the buyer when the buyer inspections commence. At this point, the supplier must go through all the inspections, measurements and tests they have already performed during building and collect the reports to be delivered to the buyer. The supplier's own inspections, functional tests and other tests must be timed so that any issues discovered can be corrected before the buyer inspections commence Functional tests of installed equipment After the equipment and systems have been installed, each device and system must be inspected and tested by the supplier. During the inspection, the goal is to ensure that the device is correctly and carefully installed and attached and that it functions correctly. When installing advanced systems and checking their functionality, the supplier must make use of the services of the importer or another expert on the system/device if the systems or their complexity so require. These types of systems include e.g. the extensive navigation and communication systems installed in larger vessels. The commissioning inspections of the main engines (excl. outboard engines under 140 kw) must always be performed by the importer or their representative (the supplier may not do this themselves even if they have authorization from the importer). Especially with regard to more extensive navigation and communication systems, the supplier must discuss the way the systems are intended to work with the buyer before the inspections are commenced in order to ensure that the systems and equipment function correctly Inventory and inspection of the boat's equipment and equipment mounting functionality tests Before the buyer's technical acceptance inspections the supplier must ensure that all of the equipment mentioned in the technical specification are placed in their appointed locations on the vessel. In addition to the fact that the equipment is present, attention should also be paid to their condition and tidiness as well as the functionality of their mountings. 10 / 21

11 3.2 The buyer's technical acceptance inspections After the supplier has performed their own inspections, the buyer will perform similar acceptance-related inspections as spot checks. The buyer will base its inspections and their extent on the inspection and testing records delivered by the supplier. If the buyer is unable to confirm the reliability of the supplier's inspections through spotchecking, the buyer may also perform a full-scale inspection. Especially for the first vessel in a series, the buyer will perform more extensive inspections. 3.3 Tests and measurements to be taken at the time of acceptance of the vessel During the acceptance inspection, the following tests and measurements will be performed and recorded. The measurement reports must also include the measuring results (not just accepted/failed). The measurements must be performed using calibrated equipment. The supplier will present the buyer with calibration certificates Docking tests Under the supervision and guidance of the buyer's representative, at least the following docking tests must be performed. In other respects, the Commercial Craft Rules' requirements must be complied with Drop test If the vessel is classified as a vessel that requires a "drop-test" or the hull is made from a material whose strength cannot, according to the Commercial Craft Rules, be checked based on calculations (e.g. polyethylene), a drop test must be performed. The drop test must be carried out according to the Commercial Craft Rules' requirements and the definitions of the ISO or ISO 6185 (RIB boats) standards. The drop test will only be performed on the first vessel in a series. If the supplier has already had a drop test performed on a similar vessel and its hull, the documented results of a previous drop test can be recognized. If there are significant changes to the hull's or vessel's structure, a new test must be performed Weighing The vessel will be weighed at launch to determine its total weight. The weighing will be done as a 1-point lift and, depending on the vessel, the supplier needs to provide appropriate lifting equipment for the weighing (crane, lifting lines or chains, suitable shackles and, if necessary, a lifting boom or frame). During the lift the boat's tanks must be filled according to the test drive weights given in the technical specification. 11 / 21

12 The vessel will be weighed twice and the average result from the two weighings will be recorded. The weighing will be performed using the buyer's scale, unless otherwise agreed with the buyer. If the weighing results differ significantly from each other considering the size and weight of the vessel, the reason for the difference must be found and the vessel weighed several more times to ensure that the result is correct Leak tightness tests Leak tightness tests will be performed on those parts of the vessel that are above the hull waterline to ensure the leak tightness of the deck and deck structures as well as the windows, doors and hatches. Pressurized water shall be sprayed at the vessel from several directions and, depending on the size of the vessel, for roughly 0.5 h (the water shall not, however, be high-pressure water from e.g. a pressure washer). The structures, windows, hatches and doors must not allow the water to leak into the boat or into the deck storage compartments. If any leaks are found, their causes must be found and repairs performed. After this, the leak tightness test needs to be repeated for the repaired areas Stability tests The vessel shall be stability tested according to the Commercial Craft Rules' requirements to ensure that the vessel meets the stability requirements. The testing procedure depends on the size and structure of the vessel (e.g. tilting tests, gunwale load tests, freeboard measurements, floating tests etc.). When performing these tests, care must be taken to ensure the suitability of the location and weather for testing purposes. The testing will be performed by an inspection body selected by the buyer. The costs charged by the inspection body are the buyer's responsibility. If no inspection in accordance with the regulations controlling the building of the vessel needs to be performed according to the procurement contract, the buyer will perform these tests Corrosion protection measurements (vessel with a metal hull) Corrosion protection measurements (hull potential measurements) are to be performed to ensure that there are a sufficient amount of protective anodes as well as to prevent overprotection. 12 / 21

13 The measurements are to be performed by measuring the potential difference between the sea water and the measuring point following the principles and measurement values of standard SFS The measurements shall be taken using a voltage meter with high internal resistance and a silver/silver chloride electrode. The measurements shall be performed at six points on the deck of the vessel; at the bow, stern and two points on both sides. The measuring electrode shall be lowered by its cable to roughly 1.5 m depth at each measuring point. After that there should be a wait of roughly 0.5 min to allow the electrode to stop moving before recording the value. The buyer must explicitly approve the testing method and procedure. All of the measured values must be within the ranges given in the SFS standard. If these values cannot be reached during the measuring process, the parties will agree on corrective actions and the inspection of the results of these corrective actions. The measurements shall only be performed in seawater. If the supplier has no access to seawater (a lake, river or river delta), the measurements shall be taken after the vessel has been accepted, in the vessel's home port. In this case, during acceptance the lack of measurements will be recorded and a reservation for any potentially necessary corrective actions shall be included in the acceptance records or the related defect list. If the supplier does not have a silver/silver chloride electrode, the measurements can be taken using the buyer's electrode Battery load testing The vessel's batteries shall be load tested in compliance with the Commercial Craft Rules' guidelines. Under the largest possible load (situation: navigation in the dark) the battery voltage must not drop below the nominal voltage during two hours Bilge pump and bilge water level sensor function tests After the launch, the emptying systems of all the vessel's compartments shall be tested (excl. the pontoons of RIB boats or RIB-type boats or inflatable sections in the vessel) During testing, the actual functionality of every bilge pump and the correct control and alarm limits of the water level sensors will be tested. The testing is performed by filling, one by one, each compartment's bilge with enough fresh water to check the functioning of the bilge pumps and water level sensors. Sea water shall not be used so the bilges remain clean. During the test it is especially important to ensure that the water level sensors start the bilge pumps at the correct point and turn them off once the bilge is empty. If the vessel's bilge system is equipped with a separate alarm that is set off when a bilge pump starts up (see technical specification), the alarm functions must be tested as well. 13 / 21

14 3.3.2 Sea trials Under the supervision and guidance of the buyer's representative, at least the following sea trials must be performed. In other respects, the Commercial Craft Rules' requirements must be complied with. Before the sea trials, the supplier must break in the main engines according to the manufacturer's instructions so that the sea trials can be performed according to the schedule without the limitations caused by the break-in phase. Note that during the test drives performed before the acceptance of the vessel all of the maritime rescue markings mentioned in the technical specification (the MERIPELASTUS and SAR texts) and the unit ID of the vessel must be reliably covered. The other option is to install these texts just before the vessel's acceptance. During the speed measurements and other weather-dependent measurements the wind speed may be max. 5 m/s and wave height max. roughly 0.5 m. The tests are to be performed in compliance with the Commercial Craft Rules. The vessel must behave in a logical manner during all tests and in all conditions Main engine performance tests The sea trial must last at least 2 hours. During the trial run, engine function will be monitored and the operating values recorded. During the trial run, the engines will be used at full power for at least half an hour. The goal of the testing is specifically to ensure that there are no fluid leaks, loose mountings or other issues with the engine Main engine installation inspection and functional analysis An installation inspection and functional analysis shall be performed on the main engines (excl. outboard engines under 140 kw) by the engine manufacturer or the importer's authorized representative (the supplier may not do this themselves even if they have the manufacturer's authorization). The goal of the inspection is to ensure that the engines are dimensioned and mounted on the vessel correctly and according to the manufacturer's instructions. The inspection and functional analysis is performed according to the engine manufacturer's instructions and considering the minimum requirements presented below. The inspector will create and sign inspection and functional analysis records that confirm the correct installation and dimensioning of the engines. The measured values will also be attached to the records. 14 / 21

15 The functional analysis must include at least the following measurements: measurement of the boost pressures (turbocharged diesel engines, excl. outboard engines without a measuring possibility) measurement of exhaust temperatures at the turbocharger outputs or the exhaust pipe bend (excl. outboard engines) measurement of lubricant pressures (in outboard engines only if there is a measuring possibility) measurement of coolant pressures (in outboard engines only if there is a measuring possibility) checking the engine RPM's when engaging gears and under different loads checking that the main engines reach the minimum max. RPM's defined by the manufacturer and that the engines do not go into overdrive measurement of back pressure (excl. outboard engines) measurement of the engine room and intake air temperatures (excl. outboard engines) 3.4 Inspections The buyer's sea trial Before the buyer's sea trial the supplier must have, during their own sea trials, ensured that the vessel meets the buyer's requirements. The buyer's sea trial will be carried out according to a separate sea trial schedule (attachment 2). The sea trial required for the final inspection carried out by the inspection body selected by the buyer can be performed at the same time or as a separate trial run. During the sea trial required for a final inspection according to the Commercial Craft Rules, tests required by the Commercial Craft Rules for the approval of the vessel will be performed The SMPS basic inspection After the aforementioned inspections, the buyer will arrange a basic inspection under the Finnish Lifeboat Institution's (SMPS) inspection system. The inspection will be performed by an SMPS vessel inspector or SMPS's own inspector. Arranging the inspection and covering the inspector's costs are the buyer's responsibilities Inspection by the Finnish Transport Safety Agency Trafi If the technical specification classifies the vessel as a vessel that must be inspected according to the inspection system of the Finnish Transport Safety Agency Trafi, the buyer will also arrange this inspection once the previous inspections have been performed. The inspection will be carried out by Trafi's own inspector or an inspector authorized by Trafi. 15 / 21

16 3.5 Trial period Arranging the inspection and covering the inspector's costs are the buyer's responsibilities. If a trial period for the first vessel in a series has been agreed on in the procurement contract, the buyer will make use of this trial period before the vessel is accepted. The length of the trial period is at least three (3) weeks unless otherwise agreed in the procurement contract. During the trial period the buyer will perform their own tests and trials according to their own trial schedule, including typical maritime rescue and assistance missions. This allows the buyer to ensure that the vessel functions as intended and specifically meets the goals and requirements set for the vessel. The trial period also provides better opportunities for assessing the vessel's true performance in various conditions that are rarely present during the acceptance-related sea trials. A longer trial period will also help the buyer discover weaknesses in the vessel or the vessel series that cannot be discovered during normal acceptance inspections. The location for the trial period is defined in the procurement contract. Unless otherwise agreed in the procurement contract or between the buyer and the supplier during the building process, the supplier will deliver the boat to the trial period location. If necessary, the supplier is also responsible for transporting the vessel back to the shipyard after the trial period. All defects discovered during the trial period shall be recorded by the buyer and then corrected by the supplier before the vessel is delivered. If during the trial period any defects or other issues requiring corrective action are discovered that have to do with an inadequate or flawed technical specification or solutions separately approved by the buyer during the construction of the vessel, the buyer will decide whether these should be corrected as additional or modification work. The additional or modification work shall, as a rule, be performed before the acceptance of the vessel unless their scale of the work requires the buyer and supplier to agree that it will be done after the acceptance. The buyer is responsible for expenses resulting from the use of the vessel during the trial period. In addition, the buyer has the liability for risk and is responsible for insuring the boat according to the SMPS Procurement Guide during the trial period. 4. DELIVERY DOCUMENTATION The supplier will deliver the complete delivery documentation in accordance with the procurement contract, the SMPS Procurement Guide and the approved work phase schedule (or a separate acceptance schedule). In principle, the delivery documentation will always be delivered before the acceptance of the vessel, unless otherwise agreed in the procurement contract (see the SMPS Procurement Guide). In some cases it may have been agreed in the procurement contract that the delivery documentation for the first vessel in a series shall only be handed over after the acceptance, within an agreed timeframe. 16 / 21

17 The applicable parts of this specification are to be complied with also when overhauling or updating the buyer's vessels. In this case, the delivery documentation only consists of the materials related to the work done by the supplier and the updating of the vessel's existing documentation so it reflects the changes. The extent of work to be performed during updates or overhauls shall be agreed in a procurement contract. 4.1 Delivery documentation list The delivery documentation must include at least the following: table of contents user manual (written together with the buyer and according to their instructions, based on the Recreational Craft Directive's requirements) updated technical specification (provided by the buyer) equipment warranty certificates product certificates conformity certificates the supplier's own work inspection records measurement records sea trial records (provided by the buyer) inspection body inspection report (provided by the inspection body selected by the buyer) stability and leak tightness reports (provided by the inspection body selected by the buyer if an inspection by such a body was included, otherwise provided by the supplier) other documentation related to the delivery all the drawings, lists, calculations and tables used during construction (excl. materials that the supplier considers confidential) confidential materials (materials that the supplier considers confidential shall be clearly marked as NOT PUBLIC and only delivered as a part of one office set) use, maintenance and installation manuals for all the equipment installed in the vessel, including any independent purchases by the buyer (in this case the buyer will deliver the materials to the supplier) The guide of contents templates for the folders of the paper version of the delivery documentation and the folder structure model for the electronic delivery documentation can be found attached to this document (attachment 3). The buyer will manage and archive the delivery documentation of their vessels electronically in their own operations control system. Due to this, it is very important to deliver the documentation in the requested format and organized according to the provided table of contents. The delivery documentation, including the use, maintenance and installation manuals etc., must concern the particular delivered vessel and the equipment installed in it. If no electronic documentation is available for some equipment, the supplier needs to scan the documentation into an electronic format. 17 / 21

18 The supplier should start collecting the delivery documentation as soon as the equipment and systems are ordered so that all documentation is available before the acceptance of the vessel. The supplier is also responsible for collecting the use, maintenance and installation manuals for any independent purchases the buyer has made when the equipment or systems are delivered or, at the latest, when they are installed. This is to prevent the documentation from being lost or stained during construction. The supplier must collect the documentation for their own individual purchases in an electronic format and send them to the buyer to be included in the delivery documentation. All delivery documentation will be delivered in Finnish if the supplier is Finnish or the vessel is manufactured in Finland, unless otherwise agreed with the buyer. If an equipment supplier does not provide documentation in Finnish some equipment, the documentation may also be in English. If the supplier is not Finnish or the vessel is mostly built outside Finland, the materials may also be in English. This does not, however, include the user manual, safety plan or other safety-related materials or the contents of the plate list, which must always be in Finnish (all markings on the vessel shall be in Finnish). The delivery documentation will be delivered as two electronic sets and as one coherent paper set stored in folders and organized according to the table of contents provided by the buyer. One of the electronic delivery documentation sets is a so-called office set, which will include all the documentation created during the construction by the supplier or the equipment suppliers. The other electronic set and the paper set are for the vessel's users ( boat set ), and shall not include any plans that are considered confidential. The number of the delivery documentation folders depends on the size of the vessel and the amount of delivery documentation. The folders will be equipped with a fly leaf and tabs showing the table of contents. The table of contents must follow the table of contents template provided by the buyer. 4.2 Electronic delivery documentation format The formats for the electronic materials delivered by the supplier are as follows: user manual, technical specification word (office set) user manual, technical specification pdf (office set and boat set) warranty certificates, product certificates, conformity certificates pdf inspection and measuring records pdf the inspection body's inspection report and leak tightness report pdf lists, calculations and tables - excel (office set) lists, calculations and tables - pdf (office set and boat set) drawings AutoCad (version: 2013 or newer unless otherwise agreed) and pdf (office set) drawings pdf (series of vessels) use, maintenance and installation instructions pdf If the vessel includes automation systems that the supplier is responsible for (e.g. a bus controlled electrical system) or other similar systems, the supplier must also provide, as 18 / 21

19 separate files and in the correct format, the most recent programming backups for all of the systems' components. 4.3 Inspection of delivery documentation Before approving the delivery documentation, the buyer will inspect all of the delivery documentation. The delivery documentation must be handed over to the buyer for inspection in its entirety as a paper and electronic version ("office set") by the latest on the date when the buyer starts the acceptance inspections (see section 3). The buyer reserves at least three (3) weeks for the inspection of the documentation. If the delivery documentation for the first vessel is agreed, in the procurement contract, to be delivered only after the vessel has been accepted, the supplier must provide the buyer with the most recent drawings and other plans for the acceptance inspection, so that the buyer can inspect the vessel and drawings at the same time. In this case, the final delivery documentation inspection set will be delivered to the buyer at least three (3) weeks before the delivery documentation handover date stated in the procurement contract. The buyer will comment on the delivery documentation that has been handed over for inspection and either approves the materials or provides the supplier with a list of discovered deficiencies. The supplier will correct the deficiencies and then deliver the final delivery documentation. Once the buyer has inspected the corrections, they will explicitly approve the delivery documentation. 4.4 Changes made after the delivery documentation has been handed over If any warranty repairs or additional/modification work performed during the warranty period at the buyer's request result in changes or additions to the delivery documentation, the supplier must update the documentation. If the vessel includes systems that must be backed up, the supplier must also provide updates for the delivered back up files if they have been changed. 5. ACCEPTANCE OF THE VESSEL After the acceptance-related technical inspections, inspections and tests have been performed and any flaws or inadequacies corrected, the boat will be handed over to the buyer in a separately arranged acceptance inspection. For the acceptance inspection, the vessel must be fully completed and functional and any deficiencies must be corrected. This includes all the equipment listed in the technical specification and the delivery documentation described in this specification. When the vessel is handed over, all of its systems must be filled with the amount of water, fuel, lubricant, coolant etc. required for normal use + the additional amounts included in the delivery. Before the vessel is handed over, the supplier must clean and wash it thoroughly. Special attention shall be paid to hidden structures and all compartments. 19 / 21

20 6. USER TRAINING 6.1. Training contents 6.2 Training dates 6.3 Training resources During the acceptance inspection, the buyer will check that all of the tests and inspections listed in this specification have been performed and recorded. The supplier will create an acceptance inspection record that will be signed by the representatives of both the buyer and the supplier. When the report is signed, the ownership of the boat is transferred to the buyer. The liability for risk is transferred as described in the SMPS Procurement Guide. During the acceptance inspection the supplier will also provide the buyer with a signed delivery certificate that includes at least the information required for the vessel's registration by the Finnish Transport Safety Authority Trafi and any necessary attachments. Unless otherwise agreed in the procurement contract, the buyer and supplier will together arrange user training in order to teach the correct use and maintenance of the vessel and its equipment to the future crew and maintenance crew. For a series of vessels, the trainings will be either arranged for each vessel or, should the vessels' completion schedule allow it, for several vessels at a time. In addition to general information on the vessel and its structure, the training must cover all of the vessel's systems and equipment to the extent that the buyer feels is necessary in order to ensure the correct use and maintenance of the vessel. During the training, special attention shall be paid to all training regarding the main and auxiliary engines, transmission, propulsion and navigation and communication electronics. In vessels that have bus-controlled electric systems, the bus control structure, function and maintenance must also be covered to an adequate extent. The user training must include theoretical training on the vessel and its structures in a classroom as well as training on the same subjects at the docked vessel. In addition, training regarding the manoeuvring of the vessel and rescue and assistance missions shall be provided at sea. The buyer will explicitly confirm the number of persons participating in the training. Usually the number of people participating in the training will be limited to max. the number of people who can be in the vessel during the training at sea. An example of a user training schedule is attached to this document (attachment 4). The training dates and the number of vessels participating in each user training will be decided by the buyer well in advance before the vessels are completed according to the building schedule. The user training should be timed as soon after the acceptance of the vessel as possible, though only during the open water season. The supplier will use their own training resources to provide training on the subjects that the supplier has experts on. Equipment manufacturer representatives or other experts 20 / 21

21 6.4 Training location 6.5 Training costs shall be used as trainers for the parts that the supplier's personnel is not qualified to provide training for. The supplier is responsible for their own representatives and equipment manufacturer representatives and reserving them for the trainings. The buyer will arrange the trainers that will cover the buyer's independent purchases. The buyer is also responsible for arranging driving and manoeuvring training and rescue activity training. Depending on the size of the vessel, the duration of the training will be 2 4 days. The supplier must reserve at least one day for their portion of the training and must be prepared for the training to be arranged on a weekend. The training will normally be provided in Finnish. For some individual experts' sections, it is possible to agree that the expert may use English. The training will be arranged at a location announced by the buyer (usually the buyer's own operation and training centre or, if it is unavailable, at the vessel's future home port or another location chosen by the buyer). If so agreed, the training can also be arranged at the supplier's facilities. The supplier is responsible for the costs charged by their own trainers and any experts the supplier is responsible for. The buyer is responsible for the costs charged by their own trainers and the training resources required by their separate purchases. The buyer is responsible for covering the travel, accommodation and food costs of the persons participating in the training. If the user training is arranged at the buyer's operation and training centre, the supplier's trainers and experts invited by the supplier will be offered food and accommodations by the buyer. If the training is arranged at the supplier's facilities, the supplier is responsible for reserving suitable facilities and covering the resulting costs. The buyer is responsible for the transport costs of the vessel or vessels used in the training. 21 / 21

National Building Code of Finland, Part D1, Building Water Supply and Sewerage Systems, Regulations and guidelines 2007

National Building Code of Finland, Part D1, Building Water Supply and Sewerage Systems, Regulations and guidelines 2007 National Building Code of Finland, Part D1, Building Water Supply and Sewerage Systems, Regulations and guidelines 2007 Chapter 2.4 Jukka Räisä 1 WATER PIPES PLACEMENT 2.4.1 Regulation Water pipe and its

Lisätiedot

LUONNOS RT 80260 EN AGREEMENT ON BUILDING WORKS 1 THE PARTIES. May 1998 1 (10)

LUONNOS RT 80260 EN AGREEMENT ON BUILDING WORKS 1 THE PARTIES. May 1998 1 (10) RT 80260 EN May 1998 1 (10) AGREEMENT ON BUILDING WORKS This agreement template is based on the General Terms and Conditions of Building Contracts YSE 1998 RT 16-10660, LVI 03-10277, Ratu 417-7, KH X4-00241.

Lisätiedot

TIEKE Verkottaja Service Tools for electronic data interchange utilizers. Heikki Laaksamo

TIEKE Verkottaja Service Tools for electronic data interchange utilizers. Heikki Laaksamo TIEKE Verkottaja Service Tools for electronic data interchange utilizers Heikki Laaksamo TIEKE Finnish Information Society Development Centre (TIEKE Tietoyhteiskunnan kehittämiskeskus ry) TIEKE is a neutral,

Lisätiedot

LYTH-CONS CONSISTENCY TRANSMITTER

LYTH-CONS CONSISTENCY TRANSMITTER LYTH-CONS CONSISTENCY TRANSMITTER LYTH-INSTRUMENT OY has generate new consistency transmitter with blade-system to meet high technical requirements in Pulp&Paper industries. Insurmountable advantages are

Lisätiedot

Efficiency change over time

Efficiency change over time Efficiency change over time Heikki Tikanmäki Optimointiopin seminaari 14.11.2007 Contents Introduction (11.1) Window analysis (11.2) Example, application, analysis Malmquist index (11.3) Dealing with panel

Lisätiedot

Curriculum. Gym card

Curriculum. Gym card A new school year Curriculum Fast Track Final Grading Gym card TET A new school year Work Ethic Detention Own work Organisation and independence Wilma TMU Support Services Well-Being CURRICULUM FAST TRACK

Lisätiedot

Sisällysluettelo Table of contents

Sisällysluettelo Table of contents Sisällysluettelo Table of contents OTC:n Moodlen käyttöohje suomeksi... 1 Kirjautuminen Moodleen... 2 Ensimmäinen kirjautuminen Moodleen... 2 Salasanan vaihto... 2 Oma käyttäjäprofiili... 3 Työskentely

Lisätiedot

Tutkimuslääkkeiden GMP. Fimea Pirjo Hänninen

Tutkimuslääkkeiden GMP. Fimea Pirjo Hänninen Tutkimuslääkkeiden GMP Fimea 17.1.2017 Pirjo Hänninen Kliinisiä lääketutkimuksia koskeva EU:n asetus Regulation (EU) No 536/2014 Hyväksytty 16.4.2014 (voimaan 28.5. 2016) Kumoaa nykyisen lääketutkimusdirektiivin

Lisätiedot

1. SIT. The handler and dog stop with the dog sitting at heel. When the dog is sitting, the handler cues the dog to heel forward.

1. SIT. The handler and dog stop with the dog sitting at heel. When the dog is sitting, the handler cues the dog to heel forward. START START SIT 1. SIT. The handler and dog stop with the dog sitting at heel. When the dog is sitting, the handler cues the dog to heel forward. This is a static exercise. SIT STAND 2. SIT STAND. The

Lisätiedot

LX 70. Ominaisuuksien mittaustulokset 1-kerroksinen 2-kerroksinen. Fyysiset ominaisuudet, nimellisarvot. Kalvon ominaisuudet

LX 70. Ominaisuuksien mittaustulokset 1-kerroksinen 2-kerroksinen. Fyysiset ominaisuudet, nimellisarvot. Kalvon ominaisuudet LX 70 % Läpäisy 36 32 % Absorptio 30 40 % Heijastus 34 28 % Läpäisy 72 65 % Heijastus ulkopuoli 9 16 % Heijastus sisäpuoli 9 13 Emissiivisyys.77.77 Auringonsuojakerroin.54.58 Auringonsäteilyn lämmönsiirtokerroin.47.50

Lisätiedot

Choose Finland-Helsinki Valitse Finland-Helsinki

Choose Finland-Helsinki Valitse Finland-Helsinki Write down the Temporary Application ID. If you do not manage to complete the form you can continue where you stopped with this ID no. Muista Temporary Application ID. Jos et onnistu täyttää lomake loppuun

Lisätiedot

Network to Get Work. Tehtäviä opiskelijoille Assignments for students. www.laurea.fi

Network to Get Work. Tehtäviä opiskelijoille Assignments for students. www.laurea.fi Network to Get Work Tehtäviä opiskelijoille Assignments for students www.laurea.fi Ohje henkilöstölle Instructions for Staff Seuraavassa on esitetty joukko tehtäviä, joista voit valita opiskelijaryhmällesi

Lisätiedot

Olet vastuussa osaamisestasi

Olet vastuussa osaamisestasi Olet vastuussa osaamisestasi Ohjelmistoammattilaisuuden uudet haasteet Timo Vehmaro 02-12-2015 1 Nokia 2015 Mitä osaamista tulevaisuudessa tarvitaan? Vahva perusosaaminen on kaiken perusta Implementaatio

Lisätiedot

Capacity Utilization

Capacity Utilization Capacity Utilization Tim Schöneberg 28th November Agenda Introduction Fixed and variable input ressources Technical capacity utilization Price based capacity utilization measure Long run and short run

Lisätiedot

ETELÄESPLANADI 2 00130 HELSINKI

ETELÄESPLANADI 2 00130 HELSINKI 00130 HELSINKI MODERNIA TOIMISTOTILAA Noin VUOKRATAAN Ainutlaatuinen tilaisuus vuokrata huipputason Helsingin näköalapaikalta Toimi pian! Lisätietoja KALLE JASKARA Myyntijohtaja +358 50 324 0404 kalle.jaskara@tkoy.fi

Lisätiedot

FinFamily PostgreSQL installation ( ) FinFamily PostgreSQL

FinFamily PostgreSQL installation ( ) FinFamily PostgreSQL FinFamily PostgreSQL 1 Sisällys / Contents FinFamily PostgreSQL... 1 1. Asenna PostgreSQL tietokanta / Install PostgreSQL database... 3 1.1. PostgreSQL tietokannasta / About the PostgreSQL database...

Lisätiedot

The CCR Model and Production Correspondence

The CCR Model and Production Correspondence The CCR Model and Production Correspondence Tim Schöneberg The 19th of September Agenda Introduction Definitions Production Possiblity Set CCR Model and the Dual Problem Input excesses and output shortfalls

Lisätiedot

4x4cup Rastikuvien tulkinta

4x4cup Rastikuvien tulkinta 4x4cup Rastikuvien tulkinta 4x4cup Control point picture guidelines Päivitetty kauden 2010 sääntöihin Updated for 2010 rules Säännöt rastikuvista Kilpailijoiden tulee kiinnittää erityistä huomiota siihen,

Lisätiedot

On instrument costs in decentralized macroeconomic decision making (Helsingin Kauppakorkeakoulun julkaisuja ; D-31)

On instrument costs in decentralized macroeconomic decision making (Helsingin Kauppakorkeakoulun julkaisuja ; D-31) On instrument costs in decentralized macroeconomic decision making (Helsingin Kauppakorkeakoulun julkaisuja ; D-31) Juha Kahkonen Click here if your download doesn"t start automatically On instrument costs

Lisätiedot

Sisävesidirektiivin soveltamisala poikkeussäännökset. Versio: puheenjohtajan ehdotus , neuvoston asiakirja 8780/16.

Sisävesidirektiivin soveltamisala poikkeussäännökset. Versio: puheenjohtajan ehdotus , neuvoston asiakirja 8780/16. Sisävesidirektiivin soveltamisala poikkeussäännökset Versio: puheenjohtajan ehdotus 13.5.2016, neuvoston asiakirja 8780/16. Artikla 2 1. This Directive applies to deck crew members, radio operators, liquefied

Lisätiedot

Alternative DEA Models

Alternative DEA Models Mat-2.4142 Alternative DEA Models 19.9.2007 Table of Contents Banker-Charnes-Cooper Model Additive Model Example Data Home assignment BCC Model (Banker-Charnes-Cooper) production frontiers spanned by convex

Lisätiedot

7.4 Variability management

7.4 Variability management 7.4 Variability management time... space software product-line should support variability in space (different products) support variability in time (maintenance, evolution) 1 Product variation Product

Lisätiedot

Organisaation kokonaissuorituskyvyn arviointi

Organisaation kokonaissuorituskyvyn arviointi Organisaation kokonaissuorituskyvyn arviointi Aila Järveläinen, 13.3.2018 aila.jarvelainen@trafi.fi Responsible traffic. Courage and co-operation. Hallintojärjestelmä CMS + SMS CMS SMS 29.3.2018 Finnish

Lisätiedot

KONEISTUSKOKOONPANON TEKEMINEN NX10-YMPÄRISTÖSSÄ

KONEISTUSKOKOONPANON TEKEMINEN NX10-YMPÄRISTÖSSÄ KONEISTUSKOKOONPANON TEKEMINEN NX10-YMPÄRISTÖSSÄ https://community.plm.automation.siemens.com/t5/tech-tips- Knowledge-Base-NX/How-to-simulate-any-G-code-file-in-NX- CAM/ta-p/3340 Koneistusympäristön määrittely

Lisätiedot

Lapuan myöntämä EU tuki SOLUTION asuinalueille omakoti- tai rivitaloa rakentaville

Lapuan myöntämä EU tuki SOLUTION asuinalueille omakoti- tai rivitaloa rakentaville Lapuan myöntämä EU tuki SOLUTION asuinalueille omakoti- tai rivitaloa rakentaville Pakollinen liite rakennustyön tarkastusasiakirjaan ja toiseen hakuvaiheeseen / Compulsory supplement the construction

Lisätiedot

Results on the new polydrug use questions in the Finnish TDI data

Results on the new polydrug use questions in the Finnish TDI data Results on the new polydrug use questions in the Finnish TDI data Multi-drug use, polydrug use and problematic polydrug use Martta Forsell, Finnish Focal Point 28/09/2015 Martta Forsell 1 28/09/2015 Esityksen

Lisätiedot

INSTALLATION INSTRUCTION ASENNUSOHJE PEM1417 2012-11 ENGLISH SUOMI CURRENT LIMITING DEVICE VIRTAA RAJOITTAVA SUOJA SDI46.812 & SDI46.

INSTALLATION INSTRUCTION ASENNUSOHJE PEM1417 2012-11 ENGLISH SUOMI CURRENT LIMITING DEVICE VIRTAA RAJOITTAVA SUOJA SDI46.812 & SDI46. INSTALLATION INSTRUCTION ASENNUSOHJE PEM1417 2012-11 ENGLISH SUOMI CURRENT LIMITING DEVICE VIRTAA RAJOITTAVA SUOJA SDI46.812 & SDI46.824 2/8 SDI46.812 & SDI46.824 PEM1417 2012-11 ENGLISH GENERAL INFORMATION

Lisätiedot

HITSAUKSEN TUOTTAVUUSRATKAISUT

HITSAUKSEN TUOTTAVUUSRATKAISUT Kemppi ARC YOU GET WHAT YOU MEASURE OR BE CAREFUL WHAT YOU WISH FOR HITSAUKSEN TUOTTAVUUSRATKAISUT Puolitetaan hitsauskustannukset seminaari 9.4.2008 Mikko Veikkolainen, Ratkaisuliiketoimintapäällikkö

Lisätiedot

FIS IMATRAN KYLPYLÄHIIHDOT Team captains meeting

FIS IMATRAN KYLPYLÄHIIHDOT Team captains meeting FIS IMATRAN KYLPYLÄHIIHDOT 8.-9.12.2018 Team captains meeting 8.12.2018 Agenda 1 Opening of the meeting 2 Presence 3 Organizer s personell 4 Jury 5 Weather forecast 6 Composition of competitors startlists

Lisätiedot

Information on preparing Presentation

Information on preparing Presentation Information on preparing Presentation Seminar on big data management Lecturer: Spring 2017 20.1.2017 1 Agenda Hints and tips on giving a good presentation Watch two videos and discussion 22.1.2017 2 Goals

Lisätiedot

2017/S Contract notice. Supplies

2017/S Contract notice. Supplies Supplies 153936 2017 25/04/2017 S80 - - Supplies - Contract notice - Open procedure I. II. III. IV. VI. -: Medical equipments, pharmaceuticals and personal care products 2017/S 080-153936 Contract notice

Lisätiedot

Miehittämätön meriliikenne

Miehittämätön meriliikenne Rolls-Royce & Unmanned Shipping Ecosystem Miehittämätön meriliikenne Digimurros 2020+ 17.11. 2016 September 2016 2016 Rolls-Royce plc The 2016 information Rolls-Royce in this plc document is the property

Lisätiedot

Other approaches to restrict multipliers

Other approaches to restrict multipliers Other approaches to restrict multipliers Heikki Tikanmäki Optimointiopin seminaari 10.10.2007 Contents Short revision (6.2) Another Assurance Region Model (6.3) Cone-Ratio Method (6.4) An Application of

Lisätiedot

SESKO ry LAUSUNTOPYYNTÖ 7/08 LIITE Toimisto (5) HUOM. Komiteoiden ja seurantaryhmien kokoonpanot on esitetty SESKOn komitealuettelossa

SESKO ry LAUSUNTOPYYNTÖ 7/08 LIITE Toimisto (5) HUOM. Komiteoiden ja seurantaryhmien kokoonpanot on esitetty SESKOn komitealuettelossa 2008-07-25 1(5) CENELEC SC 9XB Kulkuneuvojen sähkömekaaniset materiaalit S262-08 Railway applications. Rolling stock. Pantographs. Characteristics and tests. Part 1: Pantographs for main line vehicles

Lisätiedot

SOTILASILMAILUTIEDOTE SIM-TO-LT-001 HENKILÖSTÖVAATIMUSTEN SOVELTAMINEN,

SOTILASILMAILUTIEDOTE SIM-TO-LT-001 HENKILÖSTÖVAATIMUSTEN SOVELTAMINEN, SOTILASILMAILUN VIRANOMAISYKSIKKÖ SOTILASILMAILUTIEDOTE 11.05.2018 PL 30, 41161, puh. 0299 800, faksi 0299 291 929, s-posti fimaa@mil.fi SOTILASILMAILUTIEDOTE SIM-TO-LT-001 HENKILÖSTÖVAATIMUSTEN SOVELTAMINEN,

Lisätiedot

16. Allocation Models

16. Allocation Models 16. Allocation Models Juha Saloheimo 17.1.27 S steemianalsin Optimointiopin seminaari - Sks 27 Content Introduction Overall Efficienc with common prices and costs Cost Efficienc S steemianalsin Revenue

Lisätiedot

Information on Finnish Language Courses Spring Semester 2018 Päivi Paukku & Jenni Laine Centre for Language and Communication Studies

Information on Finnish Language Courses Spring Semester 2018 Päivi Paukku & Jenni Laine Centre for Language and Communication Studies Information on Finnish Language Courses Spring Semester 2018 Päivi Paukku & Jenni Laine 4.1.2018 Centre for Language and Communication Studies Puhutko suomea? -Hei! -Hei hei! -Moi! -Moi moi! -Terve! -Terve

Lisätiedot

Salasanan vaihto uuteen / How to change password

Salasanan vaihto uuteen / How to change password Salasanan vaihto uuteen / How to change password Sisällys Salasanakäytäntö / Password policy... 2 Salasanan vaihto verkkosivulla / Change password on website... 3 Salasanan vaihto matkapuhelimella / Change

Lisätiedot

Gap-filling methods for CH 4 data

Gap-filling methods for CH 4 data Gap-filling methods for CH 4 data Sigrid Dengel University of Helsinki Outline - Ecosystems known for CH 4 emissions; - Why is gap-filling of CH 4 data not as easy and straight forward as CO 2 ; - Gap-filling

Lisätiedot

Introduction to Automotive Structure

Introduction to Automotive Structure Supakit Rooppakhun Introduction to Automotive Structure The main purpose is to: Support all the major components and sub assemblies making up the complete vehicle Carry the passengers and/or payload in

Lisätiedot

MIKES, Julkaisu J3/2000 MASS COMPARISON M3. Comparison of 1 kg and 10 kg weights between MIKES and three FINAS accredited calibration laboratories

MIKES, Julkaisu J3/2000 MASS COMPARISON M3. Comparison of 1 kg and 10 kg weights between MIKES and three FINAS accredited calibration laboratories MITTATEKNIIKAN KESKUS CENTRE FOR METROLOGY AND ACCREDITATION Julkaisu J3/2000 MASS COMPARISON M3 Comparison of 1 kg and 10 kg weights between MIKES and three FINAS accredited calibration laboratories Kari

Lisätiedot

TEST REPORT Nro VTT-S Air tightness and strength tests for Furanflex exhaust air ducts

TEST REPORT Nro VTT-S Air tightness and strength tests for Furanflex exhaust air ducts TEST REPORT Nro VTT-S-04515-08 19.5.008 Air tightness and strength tests for Furanflex exhaust air ducts Requested by: Hormex Oy TEST REPORT NRO VTT-S-04515-08 1 () Requested by Order Hormex Oy Linnanherrankuja

Lisätiedot

Administrative Guidelines for Asia Programme

Administrative Guidelines for Asia Programme Administrative Guidelines for Asia Programme Administrative guidelines Guidelines by call / year of receiving funding http://www.cimo.fi/ohjelmat/aasia_ohjelma/osallistujalle Funding can not be used to

Lisätiedot

Microsoft Lync 2010 Attendee

Microsoft Lync 2010 Attendee VYVI MEETING Lync Attendee 2010 Instruction 1 (15) Microsoft Lync 2010 Attendee Online meeting VYVI MEETING Lync Attendee 2010 Instruction 2 (15) Index 1 Microsoft LYNC 2010 Attendee... 3 2 Acquiring Lync

Lisätiedot

Hankintailmoitus: Pohjois-Savon sairaanhoitopiirin kuntayhtymä/kiinteistöyksikkö : Puijon sairaalan Pääaula-alueen uudistus, Sähköurakka

Hankintailmoitus: Pohjois-Savon sairaanhoitopiirin kuntayhtymä/kiinteistöyksikkö : Puijon sairaalan Pääaula-alueen uudistus, Sähköurakka Finland Tender Hankintailmoitus: Pohjois-Savon sairaanhoitopiirin kuntayhtymä/kiinteistöyksikkö : Puijon sairaalan Pääaula-alueen uudistus, Sähköurakka Tarjoukset 6.5.2011 klo 15.00 mennessä osoitteeseen:

Lisätiedot

AKKREDITOITU TARKASTUSLAITOS ACCREDITED INSPECTION BODY DEKRA INSPECTION OY

AKKREDITOITU TARKASTUSLAITOS ACCREDITED INSPECTION BODY DEKRA INSPECTION OY I047/M02/2016 Liite 1 / Appendix 1 Sivu / Page 1(6) AKKREDITOITU TARKASTUSLAITOS ACCREDITED INSPECTION BODY DEKRA INSPECTION OY Tunnus Code Tarkastuslaitos Inspection body Osoite Address www www I047 DEKRA

Lisätiedot

TÄYTTÖAUTOMAATIT TÄYTTÖAUTOMAATIT COMPUTER INFLATORS

TÄYTTÖAUTOMAATIT TÄYTTÖAUTOMAATIT COMPUTER INFLATORS 31 S AHCON computer inflators are designed with a view to high quality, precision and long service life. The inflation computers are designed in Denmark and manufactured and tested in our own workshop.

Lisätiedot

Transport validation. Anne Junttonen Finnish Medicines Agency Copenhagen

Transport validation. Anne Junttonen Finnish Medicines Agency Copenhagen Transport validation Anne Junttonen Finnish Medicines Agency Copenhagen 20.11.2014 Transport Validation Cannot be done? Can be done? Should be done? 20.11.2014 Anne Junttonen 2 Transport Validation Validation

Lisätiedot

Group 2 - Dentego PTH Korvake. Peer Testing Report

Group 2 - Dentego PTH Korvake. Peer Testing Report Group 2 - Dentego PTH Korvake Peer Testing Report Revisions Version Date Author Description 1.0 Henrik Klinkmann First version Table of Contents Contents Revisions... 2 Table of Contents... 2 Testing...

Lisätiedot

Information on Finnish Language Courses Spring Semester 2017 Jenni Laine

Information on Finnish Language Courses Spring Semester 2017 Jenni Laine Information on Finnish Language Courses Spring Semester 2017 Jenni Laine 4.1.2017 KIELIKESKUS LANGUAGE CENTRE Puhutko suomea? Do you speak Finnish? -Hei! -Moi! -Mitä kuuluu? -Kiitos, hyvää. -Entä sinulle?

Lisätiedot

FinFamily Installation and importing data (11.1.2016) FinFamily Asennus / Installation

FinFamily Installation and importing data (11.1.2016) FinFamily Asennus / Installation FinFamily Asennus / Installation 1 Sisällys / Contents FinFamily Asennus / Installation... 1 1. Asennus ja tietojen tuonti / Installation and importing data... 4 1.1. Asenna Java / Install Java... 4 1.2.

Lisätiedot

ReFuel 70 % Emission Reduction Using Renewable High Cetane Number Paraffinic Diesel Fuel. Kalle Lehto, Aalto-yliopisto 5.5.

ReFuel 70 % Emission Reduction Using Renewable High Cetane Number Paraffinic Diesel Fuel. Kalle Lehto, Aalto-yliopisto 5.5. ReFuel 70 % Emission Reduction Using Renewable High Cetane Number Paraffinic Diesel Fuel Kalle Lehto, Aalto-yliopisto 5.5.2011 Otaniemi ReFuel a three year research project (2009-2011) goal utilize the

Lisätiedot

You can check above like this: Start->Control Panel->Programs->find if Microsoft Lync or Microsoft Lync Attendeed is listed

You can check above like this: Start->Control Panel->Programs->find if Microsoft Lync or Microsoft Lync Attendeed is listed Online Meeting Guest Online Meeting for Guest Participant Lync Attendee Installation Online kokous vierailevalle osallistujalle Lync Attendee Asennus www.ruukki.com Overview Before you can join to Ruukki

Lisätiedot

Supplies

Supplies Supplies - 239150-2018 05/06/2018 S105 - - Supplies - Contract notice - Open procedure I. II. III. IV. VI. Finland-Oulu: Medical equipments 2018/S 105-239150 Contract notice Supplies Directive 2014/24/EU

Lisätiedot

Metsälamminkankaan tuulivoimapuiston osayleiskaava

Metsälamminkankaan tuulivoimapuiston osayleiskaava VAALAN KUNTA TUULISAIMAA OY Metsälamminkankaan tuulivoimapuiston osayleiskaava Liite 3. Varjostusmallinnus FCG SUUNNITTELU JA TEKNIIKKA OY 12.5.2015 P25370 SHADOW - Main Result Assumptions for shadow calculations

Lisätiedot

Tutkimusdata ja julkaiseminen Suomen Akatemian ja EU:n H2020 projekteissa

Tutkimusdata ja julkaiseminen Suomen Akatemian ja EU:n H2020 projekteissa Tutkimusdata ja julkaiseminen Suomen Akatemian ja EU:n H2020 projekteissa Tutkimusasiamies Kaisa Männikkö Tutkimus- ja innovaatiopalvelut Suomen Akatemian projektit Suomen Akatemia kehottaa avoimeen tieteelliseen

Lisätiedot

Jokaisella person. käyttökerralla tehtävän rutiinitarkastuksen lisäksi pätevän henkilön tulisi tehdä henkilösuojaimelle

Jokaisella person. käyttökerralla tehtävän rutiinitarkastuksen lisäksi pätevän henkilön tulisi tehdä henkilösuojaimelle Inspection Henkilösuojaimen tarkastus Tarkastusohjeet Inspection Inspection Inspection In addition to routine checks for each use, should regularly undergo a detailed inspection by a competent Jokaisella

Lisätiedot

LAADUSTA KANSAINVÄLISTÄ KILPAILUKYKYÄETUA ESITELMÄN SISÄLTÖ: 1. SABRISCAN-TARINA 2. TULOKSET 3. YHTEENVETO

LAADUSTA KANSAINVÄLISTÄ KILPAILUKYKYÄETUA ESITELMÄN SISÄLTÖ: 1. SABRISCAN-TARINA 2. TULOKSET 3. YHTEENVETO LAADUSTA KANSAINVÄLISTÄ KILPAILUKYKYÄETUA ESITELMÄN SISÄLTÖ: 1. SABRISCAN-TARINA 2. TULOKSET 3. YHTEENVETO LEAN-OPEX LEADER - koulutusohjelma on Sabriscan Oy:n 1 RATKAISULIIKETOIMINTAA LEAN-OPEX LEADER

Lisätiedot

Rotarypiiri 1420 Piiriapurahoista myönnettävät stipendit

Rotarypiiri 1420 Piiriapurahoista myönnettävät stipendit Rotarypiiri 1420 Piiriapurahoista myönnettävät stipendit Ø Rotarypiiri myöntää stipendejä sille osoitettujen hakemusten perusteella ensisijaisesti rotaryaatteen mukaisiin tarkoituksiin. Ø Stipendejä myönnetään

Lisätiedot

Tarua vai totta: sähkön vähittäismarkkina ei toimi? 11.2.2015 Satu Viljainen Professori, sähkömarkkinat

Tarua vai totta: sähkön vähittäismarkkina ei toimi? 11.2.2015 Satu Viljainen Professori, sähkömarkkinat Tarua vai totta: sähkön vähittäismarkkina ei toimi? 11.2.2015 Satu Viljainen Professori, sähkömarkkinat Esityksen sisältö: 1. EU:n energiapolitiikka on se, joka ei toimi 2. Mihin perustuu väite, etteivät

Lisätiedot

Teacher's Professional Role in the Finnish Education System Katriina Maaranen Ph.D. Faculty of Educational Sciences University of Helsinki, Finland

Teacher's Professional Role in the Finnish Education System Katriina Maaranen Ph.D. Faculty of Educational Sciences University of Helsinki, Finland Teacher's Professional Role in the Finnish Education System Katriina Maaranen Ph.D. Faculty of Educational Sciences University of Helsinki, Finland www.helsinki.fi/yliopisto This presentation - Background

Lisätiedot

C++11 seminaari, kevät Johannes Koskinen

C++11 seminaari, kevät Johannes Koskinen C++11 seminaari, kevät 2012 Johannes Koskinen Sisältö Mikä onkaan ongelma? Standardidraftin luku 29: Atomiset tyypit Muistimalli Rinnakkaisuus On multicore systems, when a thread writes a value to memory,

Lisätiedot

Ajettavat luokat: SM: S1 (25 aika-ajon nopeinta)

Ajettavat luokat: SM: S1 (25 aika-ajon nopeinta) SUPERMOTO SM 2013 OULU Lisämääräys ja ohje Oulun Moottorikerho ry ja Oulun Formula K-125ry toivottaa SuperMoto kuljettajat osallistumaan SuperMoto SM 2013 Oulu osakilpailuun. Kilpailu ajetaan karting radalla

Lisätiedot

Installation instruction PEM

Installation instruction PEM Installation instruction ASENNUSOHJE PEM1032 2010-02 SURGE ARRESTER SET FOR POLE MOUNT TRANSFORMER YLIJÄNNITESUOJASETTI PYLVÄSMUUNTAJALLE ENGLISH SUOMI 2/8 PEM1032 2010-02 ENGLISH GENERAL INFORMATION -

Lisätiedot

v INSTA-CERT Name and address of certificate holder Uponor Infra Oy Kouvolantie 365, PO Box 21 15561 Nastola Finland CERTIFICATE Date of valid edition No. 23-05-2017 2003 Date of first issue 16-06-2005

Lisätiedot

SSTY:n EMC-seminaari. EMC ja sähköisten lääkintälaitteiden standardit. Ari Honkala SESKO ry

SSTY:n EMC-seminaari. EMC ja sähköisten lääkintälaitteiden standardit. Ari Honkala SESKO ry SSTY:n EMC-seminaari EMC ja sähköisten lääkintälaitteiden standardit SESKO ry 2016-10-04 Tässä esityksessä käsitellään Yleistä täydentävistä (collateral, -1 sarja, horisontaaliset) ja eritysvaatimuksia

Lisätiedot

toukokuu 2011: Lukion kokeiden kehittämistyöryhmien suunnittelukokous

toukokuu 2011: Lukion kokeiden kehittämistyöryhmien suunnittelukokous Tuula Sutela toukokuu 2011: Lukion kokeiden kehittämistyöryhmien suunnittelukokous äidinkieli ja kirjallisuus, modersmål och litteratur, kemia, maantiede, matematiikka, englanti käsikirjoitukset vuoden

Lisätiedot

Information on Finnish Courses Autumn Semester 2017 Jenni Laine & Päivi Paukku Centre for Language and Communication Studies

Information on Finnish Courses Autumn Semester 2017 Jenni Laine & Päivi Paukku Centre for Language and Communication Studies Information on Finnish Courses Autumn Semester 2017 Jenni Laine & Päivi Paukku 24.8.2017 Centre for Language and Communication Studies Puhutko suomea? -Hei! -Hei hei! -Moi! -Moi moi! -Terve! -Terve terve!

Lisätiedot

EUROOPAN PARLAMENTTI

EUROOPAN PARLAMENTTI EUROOPAN PARLAMENTTI 2004 2009 Kansalaisvapauksien sekä oikeus- ja sisäasioiden valiokunta 2008/0101(CNS) 2.9.2008 TARKISTUKSET 9-12 Mietintöluonnos Luca Romagnoli (PE409.790v01-00) ehdotuksesta neuvoston

Lisätiedot

OP1. PreDP StudyPlan

OP1. PreDP StudyPlan OP1 PreDP StudyPlan PreDP The preparatory year classes are in accordance with the Finnish national curriculum, with the distinction that most of the compulsory courses are taught in English to familiarize

Lisätiedot

Rekisteröiminen - FAQ

Rekisteröiminen - FAQ Rekisteröiminen - FAQ Miten Akun/laturin rekisteröiminen tehdään Akun/laturin rekisteröiminen tapahtuu samalla tavalla kuin nykyinen takuurekisteröityminen koneille. Nykyistä tietokantaa on muokattu niin,

Lisätiedot

Lämmitysjärjestelmät

Lämmitysjärjestelmät METSTA Rakennusten energiatehokkuusstandardit uudistuvat seminaari 26.4.2017 Lämmitysjärjestelmät Jarek Kurnitski HEAT GAINS BUILDING PROPERTIES CLIMATIC CONDITIONS INDOOR ENVIRONMENT REQUIREMENTS EN 16789-1

Lisätiedot

Security server v6 installation requirements

Security server v6 installation requirements CSC Security server v6 installation requirements Security server version 6.4-0-201505291153 Pekka Muhonen 8/12/2015 Date Version Description 18.12.2014 0.1 Initial version 10.02.2015 0.2 Major changes

Lisätiedot

Supplies

Supplies Supplies - 239236-2018 05/06/2018 S105 - - Supplies - Contract notice - Open procedure I. II. III. IV. VI. Finland-Seinäjoki: Wheelchairs 2018/S 105-239236 Contract notice Supplies Directive 2014/24/EU

Lisätiedot

PAINEILMALETKUKELA-AUTOMAATTI AUTOMATIC AIR HOSE REEL

PAINEILMALETKUKELA-AUTOMAATTI AUTOMATIC AIR HOSE REEL MAV4 MAV5 MAV6 PAINEILMALETKUKELA-AUTOMAATTI AUTOMATIC AIR HOSE REEL Käyttöohje Instruction manual HUOMIO! Lue käyttöohjeet huolellisesti ennen laitteen käyttöä ja noudata kaikkia annettuja ohjeita. Säilytä

Lisätiedot

Automaatiojärjestelmän hankinnassa huomioitavat tietoturva-asiat

Automaatiojärjestelmän hankinnassa huomioitavat tietoturva-asiat Automaatiojärjestelmän hankinnassa huomioitavat tietoturva-asiat Teollisuusautomaation tietoturvaseminaari Purchasing Manager, Hydro Lead Buyer, Industrial Control Systems 1 Agenda / esityksen tavoite

Lisätiedot

Tynnyrivaara, OX2 Tuulivoimahanke. ( Layout 9 x N131 x HH145. Rakennukset Asuinrakennus Lomarakennus 9 x N131 x HH145 Varjostus 1 h/a 8 h/a 20 h/a

Tynnyrivaara, OX2 Tuulivoimahanke. ( Layout 9 x N131 x HH145. Rakennukset Asuinrakennus Lomarakennus 9 x N131 x HH145 Varjostus 1 h/a 8 h/a 20 h/a , Tuulivoimahanke Layout 9 x N131 x HH145 Rakennukset Asuinrakennus Lomarakennus 9 x N131 x HH145 Varjostus 1 h/a 8 h/a 20 h/a 0 0,5 1 1,5 km 2 SHADOW - Main Result Assumptions for shadow calculations

Lisätiedot

Arkkitehtuuritietoisku. eli mitä aina olet halunnut tietää arkkitehtuureista, muttet ole uskaltanut kysyä

Arkkitehtuuritietoisku. eli mitä aina olet halunnut tietää arkkitehtuureista, muttet ole uskaltanut kysyä Arkkitehtuuritietoisku eli mitä aina olet halunnut tietää arkkitehtuureista, muttet ole uskaltanut kysyä Esikysymys Kuinka moni aikoo suunnitella projektityönsä arkkitehtuurin? Onko tämä arkkitehtuuria?

Lisätiedot

LENTOTURVALLISUUSHALLINTO FLIGHT SAFETY AUTHORITY LENTOKELPOISUUSMÄÄRÄYS AIRWORTHINESS DIRECTIVE

LENTOTURVALLISUUSHALLINTO FLIGHT SAFETY AUTHORITY LENTOKELPOISUUSMÄÄRÄYS AIRWORTHINESS DIRECTIVE I L M A I L U L A I T O S CIVIL AVIATION ADMINISTRATION PL 50 FIN - 01531 VANTAA, FINLAND Puhelin/Telephone 09-82 771 International + 358 9 82 771 Telefax 09-82 772499 LENTOTURVALLISUUSHALLINTO FLIGHT

Lisätiedot

Windows Phone. Module Descriptions. Opiframe Oy puh. +358 44 7220800 eero.huusko@opiframe.com. 02600 Espoo

Windows Phone. Module Descriptions. Opiframe Oy puh. +358 44 7220800 eero.huusko@opiframe.com. 02600 Espoo Windows Phone Module Descriptions Mikä on RekryKoulutus? Harvassa ovat ne työnantajat, jotka löytävät juuri heidän alansa hallitsevat ammatti-ihmiset valmiina. Fiksuinta on tunnustaa tosiasiat ja hankkia

Lisätiedot

Helsinki Metropolitan Area Council

Helsinki Metropolitan Area Council Helsinki Metropolitan Area Council Current events at YTV The future of YTV and HKL On the initiative of 4 city mayors the Helsinki region negotiation consortiums coordinating group have presented that:

Lisätiedot

Kaivostoiminnan eri vaiheiden kumulatiivisten vaikutusten huomioimisen kehittäminen suomalaisessa luonnonsuojelulainsäädännössä

Kaivostoiminnan eri vaiheiden kumulatiivisten vaikutusten huomioimisen kehittäminen suomalaisessa luonnonsuojelulainsäädännössä M a t t i K a t t a i n e n O T M 1 1. 0 9. 2 0 1 9 Kaivostoiminnan eri vaiheiden kumulatiivisten vaikutusten huomioimisen kehittäminen suomalaisessa luonnonsuojelulainsäädännössä Ympäristöoikeustieteen

Lisätiedot

( ( OX2 Perkkiö. Rakennuskanta. Varjostus. 9 x N131 x HH145

( ( OX2 Perkkiö. Rakennuskanta. Varjostus. 9 x N131 x HH145 OX2 9 x N131 x HH145 Rakennuskanta Asuinrakennus Lomarakennus Liike- tai julkinen rakennus Teollinen rakennus Kirkko tai kirkollinen rak. Muu rakennus Allas Varjostus 1 h/a 8 h/a 20 h/a 0 0,5 1 1,5 2 km

Lisätiedot

Innovative and responsible public procurement Urban Agenda kumppanuusryhmä. public-procurement

Innovative and responsible public procurement Urban Agenda kumppanuusryhmä.   public-procurement Innovative and responsible public procurement Urban Agenda kumppanuusryhmä https://ec.europa.eu/futurium/en/ public-procurement Julkiset hankinnat liittyvät moneen Konsortio Lähtökohdat ja tavoitteet Every

Lisätiedot

TM ETRS-TM35FIN-ETRS89 WTG

TM ETRS-TM35FIN-ETRS89 WTG SHADOW - Main Result Assumptions for shadow calculations Maximum distance for influence Calculate only when more than 20 % of sun is covered by the blade Please look in WTG table WindPRO version 2.9.269

Lisätiedot

TM ETRS-TM35FIN-ETRS89 WTG

TM ETRS-TM35FIN-ETRS89 WTG SHADOW - Main Result Assumptions for shadow calculations Maximum distance for influence Calculate only when more than 20 % of sun is covered by the blade Please look in WTG table WindPRO version 2.8.579

Lisätiedot

Security server v6 installation requirements

Security server v6 installation requirements CSC Security server v6 installation requirements Security server version 6.x. Version 0.2 Pekka Muhonen 2/10/2015 Date Version Description 18.12.2014 0.1 Initial version 10.02.2015 0.2 Major changes Contents

Lisätiedot

TM ETRS-TM35FIN-ETRS89 WTG

TM ETRS-TM35FIN-ETRS89 WTG SHADOW - Main Result Assumptions for shadow calculations Maximum distance for influence Calculate only when more than 20 % of sun is covered by the blade Please look in WTG table WindPRO version 2.8.579

Lisätiedot

Data protection template

Data protection template Data protection template Aihe: rekisteriseloste ja informointipohja Topic: information about the register and information to users (related to General Data Protection Regulation (GDPR) (EU) 2016/679) Mallina

Lisätiedot

Särmäystyökalut kuvasto Press brake tools catalogue

Särmäystyökalut kuvasto Press brake tools catalogue Finnish sheet metal machinery know-how since 1978 Särmäystyökalut kuvasto Press brake tools catalogue www.aliko.fi ALIKO bending chart Required capacity in kn (T) in relation to V-opening. V R A S = plates

Lisätiedot

Travel Getting Around

Travel Getting Around - Location Olen eksyksissä. Not knowing where you are Voisitko näyttää kartalta missä sen on? Asking for a specific location on a map Mistä täällä on? Asking for a specific...wc?...pankki / rahanvaihtopiste?...hotelli?...huoltoasema?...sairaala?...apteekki?...tavaratalo?...ruokakauppa?...bussipysäkki?

Lisätiedot

I-VALO VEGA FIXING MODULE B300

I-VALO VEGA FIXING MODULE B300 Nämä ohjeet eivät välttämättä sisällä kaikkien valaisinten tai tarvikkeiden yksityiskohtaisia ohjeita, eivätkä ohjeista kaikissa asennukseen ja käyttöön tai huoltoon liittyvissä tilanteissa. / These instructions

Lisätiedot

MUSEOT KULTTUURIPALVELUINA

MUSEOT KULTTUURIPALVELUINA Elina Arola MUSEOT KULTTUURIPALVELUINA Tutkimuskohteena Mikkelin museot Opinnäytetyö Kulttuuripalvelujen koulutusohjelma Marraskuu 2005 KUVAILULEHTI Opinnäytetyön päivämäärä 25.11.2005 Tekijä(t) Elina

Lisätiedot

TM ETRS-TM35FIN-ETRS89 WTG

TM ETRS-TM35FIN-ETRS89 WTG SHADOW - Main Result Assumptions for shadow calculations Maximum distance for influence Calculate only when more than 20 % of sun is covered by the blade Please look in WTG table WindPRO version 2.8.579

Lisätiedot

Box 1. Things you have/ Pakkaus sisältää. x 4 x 16 x 4 x 4. 300mm. 1700mm. 300mm 1. Things you should know / Sinun Tulee Tietää

Box 1. Things you have/ Pakkaus sisältää. x 4 x 16 x 4 x 4. 300mm. 1700mm. 300mm 1. Things you should know / Sinun Tulee Tietää Phobos 30 Things you should know / Sinun Tulee Tietää Things you prepare / Näitä Tarvitset DURING INSTALLATION ALL PRODUCTS: use protective gloves at all times use eye protection at all times never install

Lisätiedot

Uusi Ajatus Löytyy Luonnosta 4 (käsikirja) (Finnish Edition)

Uusi Ajatus Löytyy Luonnosta 4 (käsikirja) (Finnish Edition) Uusi Ajatus Löytyy Luonnosta 4 (käsikirja) (Finnish Edition) Esko Jalkanen Click here if your download doesn"t start automatically Uusi Ajatus Löytyy Luonnosta 4 (käsikirja) (Finnish Edition) Esko Jalkanen

Lisätiedot

Työsuojelurahaston Tutkimus tutuksi - PalveluPulssi 11.3.2016. Peter Michelsson Wallstreet Asset Management Oy

Työsuojelurahaston Tutkimus tutuksi - PalveluPulssi 11.3.2016. Peter Michelsson Wallstreet Asset Management Oy Työsuojelurahaston Tutkimus tutuksi - PalveluPulssi 11.3.2016 Peter Michelsson Wallstreet Asset Management Oy Wallstreet lyhyesti Perustettu vuonna 2006, SiPa toimilupa myönnetty 3/2014 Täysin kotimainen,

Lisätiedot

WindPRO version joulu 2012 Printed/Page :47 / 1. SHADOW - Main Result

WindPRO version joulu 2012 Printed/Page :47 / 1. SHADOW - Main Result SHADOW - Main Result Assumptions for shadow calculations Maximum distance for influence Calculate only when more than 20 % of sun is covered by the blade Please look in WTG table WindPRO version 2.8.579

Lisätiedot

TM ETRS-TM35FIN-ETRS89 WTG

TM ETRS-TM35FIN-ETRS89 WTG VE1 SHADOW - Main Result Calculation: 8 x Nordex N131 x HH145m Assumptions for shadow calculations Maximum distance for influence Calculate only when more than 20 % of sun is covered by the blade Please

Lisätiedot

Kysymys 5 Compared to the workload, the number of credits awarded was (1 credits equals 27 working hours): (4)

Kysymys 5 Compared to the workload, the number of credits awarded was (1 credits equals 27 working hours): (4) Tilasto T1106120-s2012palaute Kyselyn T1106120+T1106120-s2012palaute yhteenveto: vastauksia (4) Kysymys 1 Degree programme: (4) TIK: TIK 1 25% ************** INF: INF 0 0% EST: EST 0 0% TLT: TLT 0 0% BIO:

Lisätiedot